Job costs & work in progress

Connect cost forecasts, earned revenue and billing before reviewing job margin.

Worked example · Fictional projects demonstrate cost-to-cost reporting mechanics. This schedule is an example, not a historical client result or a contract-specific accounting conclusion.

Job costs & work in progress overview

Project WIP schedule

ProjectContractCost to dateEst. total costCompleteEarned revenueBilledOverbilledUnderbilledEst. final profit
Project A$500,000$180,000$360,00050.0%$250,000$275,000$25,000$0$140,000
Project B$400,000$150,000$300,00050.0%$200,000$180,000$0$20,000$100,000
Project C$300,000$225,000$250,00090.0%$270,000$240,000$0$30,000$50,000
Total$1,200,000$555,000$910,000—$720,000$695,000$25,000$50,000$290,000

Calculation

For this example: completion = costs to date ÷ estimated total cost; earned revenue = contract value × completion. Billing above earned revenue is overbilling; billing below it is underbilling. Keep the two positions separate.

Management review

Validate remaining labor, materials, subcontract commitments and approved changes with project owners. Earned revenue less cost to date is $165,000 in this example; estimated final profit is $290,000. Review accounting treatment against the applicable contract and reporting policy.